13.03.2024
Trakcja System has signed an agreement for the following task:
Replacement of Automatic crossing systems at level crossings divided into two tasks within the project "Improving safety at level crossings - stage II"
The full scope of works will include the replacement of 17 automatic crossing systems in the IZ Wrocław area.
Within the first task, we will replace crossings on railway lines No. 137 and 275, while within the second task we will replace crossings on railway lines No. 282 and 289.
The work will be carried out for PKP PLK S.A. in a consortium with Infrakol Sp. z o.o. Sp. k. (Leader)
Deadline for completion of tasks: 410 days.