Ordering Party: TORPOL S.A.

Implementation period: September 2018 – February 2019

Scope of works: reconstruction of the overhead line with supporting structures, reconstruction of the low voltage network

Task title: Modernisation of the railway track surface and signalling equipment along with associated works on track No. 1 on the section Grabowno Wielkie – to the border of the engineering and protection area as part of the task under the following title: “Works on railway lines No. 281 and 766 on the Oleśnica/ Łukanów – Krotoszyn – Jarocin – Września – Gniezno section”.