Ordering Party: PORR S.A.

Implementation period: September 2019 – July 2021

Scope of works: comprehensive replacement of the existing overhead line in the amount of approx. 83 km, implementation of collective structure bonding in an open circuit configuration.

Task title: “Design and execution of works for the task under the title “Works on railway line No. 93 Trzebinia – Zebrzydowice on the section Trzebinia – Oświęcim – Czechowice Dziedzice” within the OPI&E 2014-2020 project No. 5.1-12 under the title “Works on railway line No. 93 on the section Trzebinia – Oświęcim – Czechowice Dziedzice”